Group Five Solar RO – Case Study

watericon-case-study

PROJECT TITLE

RO Package Plant
Refurbish and Commission

PROBLEM STATEMENT

Our client requested Watericon’s assistance with the scoping and refurbishment of 2 x water treatment containers that has been poorly maintained and possibly non-operational in the last 6-12 months. The project was based in the Limpopo region 

SOLUTION

Watericon, together with the client’s team stripped the majority of the components, compiled a comprehensive list of what was required and swiftly procured all the necessary parts locally and internationally.

PERFORMANCE AND OUTCOME

  • Plant successfully refurbished and commissioned 
  • 35-45 m3/hr water production per container ~ 90 m3/hr total 
  • Recovery of 70-75% 
  • TDS reduction of > 98% 

PROCESS

  • Borehole water from multiple sources with high conductivity (estimated feed TDS of 2000-3000)  
  • Low pressure feed pump 
  • High flow cartridges in series (20 micron 🡪 5 micron) 
  • Anti-scalant dosing 
  • Toray brackish water RO membranes

HOW OUR CLIENT BENEFITTED

Watericon will assist our clients in whichever way they require. Our flexible, customer-centric  approach  means we will go the extra mile to ensure that our clients’ projects are successful. Whether our clients require a complete rapid-deploy containerized plant or a rapid-deploy team who can lead a swift  refurbishment and optimization of such a plant, our commitment is unfaltering

Watericon’s experience and expertise makes us a valuable asset in any water related project.

 